Croydon will look for one contractor to fix its potholes, pavements and drains for up to ten years from October 2027. Cabinet approved the plan on 18 November.
Croydon Council will look for a single contractor to repair its potholes, pavements, drains and bridges for up to ten years, in a deal worth as much as £200m.
Updated 19 November: Cabinet approved the procurement plan on 18 November, subject to call-in until 26 November.
The Executive Mayor and Cabinet approved the plan on Wednesday 18 November (decision). The contractor itself will be chosen in a separate Cabinet decision (Cabinet report). The council’s current highways maintenance contract runs out on 30 September 2027.
The report says the £200m figure is “a maximum ceiling and not a guaranteed committed spend”. It is set high to cover big schemes, inflation and changes in funding over the life of the deal.
What the contract covers
The new contractor would handle almost everything the council does to keep its roads usable:
- pothole and other reactive repairs
- planned carriageway and footway works
- drainage, including gully cleaning
- winter gritting
- bridges and other structures
- inspections and emergency call-outs
Two things that are bolt-ons to the current contract would become core services: a “find and fix” pothole regime and a lump-sum arrangement for drainage.
Major infrastructure projects stay outside it. So does the A23 and the rest of the red route network, which Transport for London looks after.
How long it would run
The report recommends:
- an initial seven years, starting on or about 1 October 2027
- the option to extend by up to three more years, one year at a time
- extensions only “where performance, affordability and value for money have been demonstrated”
The money
The current contract runs within a revenue budget of £2m and a capital budget of £18m, and the new one is expected to work inside the same envelope. Revenue rates rise each year with indexation. The report warns that, given the council’s finances, contract price increases “may have to be covered from service budgets”.
Major resurfacing is paid for from the capital budget and from grants by TfL, the Department for Transport and developers. That is the money behind the 65 roads due for resurfacing this year.
The options turned down
Officers looked at five other ways of doing it and ruled them out:
- carrying on with the existing contractor beyond its term, which the report says risks being an unlawful direct award
- splitting the work into lots by area or by type of job, which contractors said would duplicate overheads and fragment accountability
- bringing the service in-house, which would need depots, vehicles, systems and staff, along with workforce and insurance liabilities. The report says the council “currently lacks the internal capacity to manage such a transition”
- two routes through existing frameworks, which the report says risk higher costs through framework fees and lose the economies of scale of one contract
Staff working on the current contract are expected to transfer to the new contractor under TUPE rules.
What it means for you
Nothing changes for nearly a year. The current contractor keeps doing the work until the end of September 2027, and you report a pothole or damaged pavement in the same way, through the council’s report a pothole page.
What the council says it wants from the new deal is faster, better-tracked repairs: “clearer accountability, stronger performance management, better cost control”. Whether that shows up on your street depends on the tender and on how much money the council has to spend each year.
What happens next
The report sets out this timetable:
- 18 November 2026: Cabinet approved the procurement plan
- 26 November 2026: last day for councillors to call the decision in
- December 2026 or January 2027: tender published
- February or March 2027: bids due
- March to April 2027: bids evaluated
- June 2027: Cabinet chooses the contractor
- October 2027: new contract starts
The decision is listed on the meeting’s agenda and decisions page.