Selhurst Road shuts under the railway bridge from 12 December to 10 January, to cars and people on foot. Network Rail is replacing the 1861 bridge.
Selhurst Road will close under the railway bridge for four weeks over Christmas and New Year. Network Rail is replacing the bridge, which was built in 1861.
The road shuts to vehicles and pedestrians from 8am on Saturday 12 December 2026 until 5pm on Sunday 10 January 2027. Network Rail announced the work on 3 November (Network Rail).
What closes, and what stays open
- Selhurst Road beneath the bridge: no vehicles and no pedestrians.
- Edith Road: closed to vehicles, with pedestrian access kept.
- Either side of the bridge: pedestrian access stays open throughout.
- Selhurst station: stays open, though Network Rail tells rail passengers to check before travelling over Christmas and New Year.
The busiest phase runs from 27 December to 2 January, when the old bridge comes out and the new one moves in. Some of that work will run around the clock. Network Rail says it will give advance notice of particularly disruptive activities.
Why it takes four weeks
Network Rail says it has “carried out multiple repairs” to the bridge and that it “has now reached the end of its serviceable life”. Lucy McAuliffe, its Sussex Route Director, said the new bridge will be assembled on site.
A heavy-lift crane would normally do the job. Engineers found utility pipes under the road, so a crane cannot safely be used. The new bridge will instead move on Self-Propelled Modular Transporters, which are remote-controlled vehicles for very heavy loads.
That method needs a longer closure. Network Rail says the alternative was “multiple weekends over many months”, and that it chose the holidays because traffic and passenger numbers are lower.
What we do not know yet
Network Rail’s announcement does not give:
- the signed diversion for drivers
- which bus routes change, or how
- the cost of the work
- the train changes on Crystal Palace home match days, which it says will be “communicated closer to the time”
The council has not yet listed a traffic order for the closure in its November notices. Network Rail says it is working with the council and emergency services on access arrangements. We will add the diversion to this page and to our Croydon roadworks page when they are published.
What it means for you
- If you drive through Selhurst, plan on no through route under the bridge from 12 December until 10 January, including the run-up to Christmas.
- If you walk under the bridge, you will need another way across the railway for those four weeks.
- If you live or work on Edith Road, ask about access now. Network Rail’s helpline is 03457 11 41 41.
- If you are going to Selhurst Park, check the road and train arrangements before each home game in that period.
Sources
- Network Rail, 3 November 2026 (dates, roads, method, the Route Director’s comments and the photograph)
- Croydon Council temporary traffic orders, November 2026 (no Selhurst Road order listed on 5 November)